transparency lab / research / equity · technology
live research note · equity · technology · march 2026

the AI compute
denominator
problem.

$310 billion committed. the supply chain to deliver it does not exist yet.

Alphabet, Microsoft, Meta, and Amazon have collectively committed more than $310 billion in capital expenditure for 2025, most of it directed at AI infrastructure. The spending is real. The commitment to investors is real. What is also real, buried in the same annual filings that announce these figures, is a set of supply chain risk disclosures that describe the precise physical constraints that make the stated deployment timelines implausible. One company makes the machines that produce leading edge chips. Three companies produce the memory those chips require. One foundry packages virtually all of them. This note is about the gap between the numerator and the denominator.

$310B+ combined 2025 AI capex guidance · Alphabet, Microsoft, Meta, Amazon
44 EUV lithography systems shipped by ASML · full year 2024 · sole source
3 companies globally that produce HBM memory · SK Hynix, Samsung, Micron
2–5 yrs average US power grid interconnection wait · new large-load data centers
supply chain map

from wafer to workload

The path from a hyperscaler's capex budget to a deployed GPU cluster passes through a surprisingly narrow set of chokepoints. ASML in the Netherlands holds a legal and technological monopoly on extreme ultraviolet lithography equipment. Without it, TSMC cannot produce the leading edge chips on which all current AI accelerators depend. TSMC's CoWoS packaging line assembles those chips with the high-bandwidth memory that makes them useful. Three memory companies produce that memory. Then the assembled hardware must be powered. The network below shows the relationships. Drag any node to explore.

hyperscaler
chip designer
foundry
HBM memory
equipment
packaging
infrastructure

01

the spending acceleration

Between fiscal year 2022 and the guidance each company has given for 2025, the four largest hyperscalers have increased their combined stated capital expenditure by roughly $190 billion. The increases are not gradual. Alphabet's capex more than doubled between 2023 and 2024, then the company guided a further 43% increase for 2025. Microsoft announced $80 billion in AI infrastructure spending for fiscal 2025 at a moment when its previous year total was $55.7 billion. These are the numbers from the filings, from the earnings calls, and from the company press releases.

figure 01
Hyperscaler capital expenditure, 2022–2025 guidance ($B)
Source: Alphabet 10-K, Microsoft 10-K, Meta 10-K, Amazon 10-K · 2025 figures are company guidance

The figure below shows each hyperscaler's 2023 capex as the background bar (baseline) and 2025 guidance as the foreground bar. The orange line marks $60 billion, the level above which each company has either reached or committed to reach.

figure 02 · 2023 actual (background) vs. 2025 guidance (foreground) · in $B · orange line = $60B
key finding

The $310 billion figure is not a prediction or an analyst estimate. It is the sum of explicit guidance given by each company's management on earnings calls or in official announcements, within months of filing the annual reports that disclose supply chain dependency risk. The same executives who described those risks guided the spending figures. The two sets of disclosures are rarely placed next to each other.


02

the physical constraints

Capital commitments are a claim on future production. Whether that production materializes depends on the physical capacity that exists or can be built in time. There are four layers where the math does not work on the stated timeline.

The first layer is lithography. ASML is the only company in the world that produces extreme ultraviolet lithography machines, the equipment that etches transistors at the dimensions required for current AI accelerators. In its 2024 annual report, ASML disclosed shipments of 44 EUV systems for the full year. Its High-NA EUV next generation tools, required for the chip geometries beyond the current generation, were just reaching initial production volumes. ASML cannot be quickly substituted. The machines take years to manufacture and require a supply chain of their own: the light source technology alone involves hundreds of specialized components from suppliers that took decades to develop.

The second layer is packaging. TSMC's CoWoS (chip on wafer on substrate) process is the packaging technology required for NVIDIA's Hopper and Blackwell GPU families. Assembling a GPU means bonding the logic die to high-bandwidth memory stacks on an interposer, then mounting the assembly on a substrate. TSMC is the primary provider of this service at scale. CoWoS capacity cannot be doubled in a quarter. New capacity requires new equipment, new cleanroom space, and a trained workforce. TSMC guided capital expenditure of $38 to $42 billion for 2025, much of it directed at capacity expansion. The packaging expansion is one of the reasons NVIDIA's Blackwell production ramp in late 2024 ran behind initial commitments.

The third layer is high bandwidth memory. HBM is the memory stack that sits adjacent to the GPU logic die and moves data fast enough to feed it. Without HBM, a Blackwell or MI300X GPU is not functional as an AI accelerator. Three companies produce HBM: SK Hynix, Samsung, and Micron. SK Hynix holds the supply relationship for NVIDIA's current H200 and B200 series. Converting standard DRAM production lines to HBM is capital intensive and takes 12 to 18 months. HBM supply was described as tight through 2025 and into 2026 in investor presentations by all three producers.

The fourth layer is power. A data center cannot operate without a grid connection, and large new loads in the United States face interconnection queues that average two to five years. In the PJM region, which includes Northern Virginia (the densest AI infrastructure market in the world), the interconnection queue had more than 280 gigawatts of pending requests as of 2024. Microsoft, Google, Amazon, and Meta have each disclosed power acquisition as a risk factor and an operational constraint in their most recent annual filings.

layer bottleneck key figure lead time sole / limited source
lithography EUV tool production 44 units shipped FY2024 Order-to-delivery: 12–18 mo. ASML only
packaging CoWoS advanced packaging ~40K wpm est. capacity 2024 New capacity: 18–24 mo. TSMC primary
memory HBM3E production 3 producers globally Line conversion: 12–18 mo. SK Hynix sole H200/B200 supplier
power Grid interconnection 280+ GW queue (PJM 2024) New interconnection: 2–5 yrs Utility dependent
what the numbers show

ASML shipped 44 EUV systems in all of 2024. That is the global ceiling on leading-edge chip production capacity additions for that year, regardless of how much money hyperscalers committed to spend. The spending commitments and the physical capacity are not in the same unit of measurement, and they are not on the same timeline.


03

NVIDIA as the clearing price

NVIDIA's FY2025 results (fiscal year ending January 2025) are the most direct measure of how much AI compute was actually delivered. Data center revenue reached $115.2 billion, up 142% from the prior year. Total revenue was $130.5 billion. Gross margin was 75.0%. These are exceptional numbers by any standard. They are also a ceiling, not a floor: NVIDIA can only recognize revenue on hardware that has been manufactured, packaged, and shipped.

figure 03
NVIDIA data center revenue vs. total revenue, FY2022–FY2025 ($B)
Source: NVIDIA FY2025 10-K (filed February 2025) · FY ending January each year

The Blackwell architecture, NVIDIA's current generation, launched in late 2024. Initial production ramps ran behind schedule, disclosed in NVIDIA's Q2 and Q3 FY2025 earnings calls, with the company attributing delays to the complexity of the new packaging design. Blackwell requires a new substrate configuration that increased the difficulty of CoWoS packaging at scale. The delays were resolved through 2024, and Blackwell shipments ramped significantly in Q4 FY2025. But the episode illustrates the mechanism: each new chip generation encounters the packaging bottleneck fresh, and resolving it takes time.

The hyperscaler order books for NVIDIA hardware extend well into 2025 and 2026. Alphabet, Microsoft, Meta, and Amazon have all disclosed NVIDIA as a critical supplier. The concentration is notable: four of the five largest companies in the world by market capitalization are dependent on a single chip designer whose production is dependent on a single foundry whose packaging line is dependent on a single memory supplier for the specific HBM variant required. At each link, there is no backup.

concentration risk

NVIDIA's FY2025 annual report (10-K, filed February 2025) discloses that its top customers accounted for 41% of total revenue. The hyperscalers do not disclose NVIDIA's share of their capex, but public supplier disclosures and data center procurement announcements suggest NVIDIA hardware accounts for a dominant share of AI infrastructure spending in 2024 and 2025. The supply chain described above is the only path to that hardware.


04

what the calls said. what the filings say.

Every one of the four hyperscalers discussed AI infrastructure spending on their most recent earnings calls. Every one of the same four companies disclosed supply chain dependency as a risk factor in the annual filings released in the same reporting period. The two sets of disclosures use different language about the same physical reality.

earnings calls — what was said
Alphabet Q4 2024 earnings call · January 2025
CEO Sundar Pichai: "We have strong conviction in the returns from these investments." CFO Anat Ashkenazi: "We expect capex to be approximately $75 billion in 2025, as we continue to invest aggressively in AI infrastructure."
Microsoft Q2 FY2025 earnings call · January 2025
CEO Satya Nadella: "We will invest $80 billion to build out AI-enabled datacenters... to train AI models and deploy AI and cloud-based applications."
Meta Q4 2024 earnings call · January 2025
CEO Mark Zuckerberg: "We're planning to spend $60 to $65 billion in capex this year... I want to make sure we are not in a position where we look back and wish we had invested more aggressively."
annual filings — what was disclosed
Alphabet FY2024 10-K · risk factors section
"We depend on third parties for critical hardware components, including semiconductors... Any disruption in our ability to procure necessary hardware... could affect our ability to build out our infrastructure."
Microsoft FY2024 10-K · risk factors section
"We are dependent on a limited number of suppliers for certain components of our hardware products, including AI chips... The supply of these components could be disrupted or limited."
Meta FY2024 10-K · risk factors section
"Our business depends on our ability to maintain and scale our technical infrastructure... supply chain disruptions, component shortages, or price increases for specialized AI hardware could negatively affect our ability to meet these needs."

The pattern is consistent across all four companies. On earnings calls: confidence, commitment, dollar figures, competitive urgency. In the annual filings: dependency on a limited number of suppliers, risk of disruption, acknowledgment that the hardware may not be available on the timelines required. Neither set of disclosures is false. They describe the same situation from two different angles, and together they define the denominator problem precisely.

earnings calls — what was said
Amazon Q4 2024 earnings call · February 2025
CEO Andy Jassy: "We have quite a bit more demand for AWS than we have capacity... Our biggest bottleneck right now in AWS is actually getting data centers and energy."
NVIDIA Q3 FY2025 earnings call · November 2024
CEO Jensen Huang: "Blackwell demand is insane... we're going to do our very best to meet demand... the supply chain is challenging but we're getting better every quarter."
annual filings — what was disclosed
Amazon FY2024 10-K · risk factors section
"Significant challenges in constructing, equipping, and operating our data centers, including obtaining sufficient power... could prevent us from meeting the growing demand for our services."
NVIDIA FY2025 10-K · risk factors section
"We are dependent on TSMC to manufacture substantially all of our products... We are also dependent on TSMC for CoWoS advanced packaging... Any disruption of these supply agreements could harm our business."
research access

The full analysis continues for subscribers.

OEM-by-OEM supply chain dependency mapping, power grid interconnection data by region, and what the next earnings cycle will likely show about unmet capex commitments.

get research access →

already a subscriber? sign in

05

what we find interesting

transparency lab · observation

What we find interesting is not the scale of the spending. Every analyst and investor has seen the capex numbers. What we find interesting is the structural relationship between the numerator and the denominator: between the commitment and the capacity.

The companies committing $310 billion in 2025 AI infrastructure spending did not invent the supply chain constraints they are operating within. Those constraints existed before the spending was announced. ASML's production schedule, TSMC's CoWoS expansion timeline, the HBM manufacturing cycle, and the US power grid interconnection queue are not surprises. They are disclosed in the same annual reports that announce the spending commitments.

What the filings show, collectively, is that all four hyperscalers simultaneously committed to spending levels that the available supply chain cannot fully service on the stated timeline. They disclosed both facts. They are disclosed in the same document. The earnings call language and the 10-K risk factor language describe the same physical reality in opposite registers.

This is not evidence of fraud or misrepresentation. Management guidance about capital expenditure is forward looking, and supply chain conditions can and do change. TSMC is expanding capacity. SK Hynix is adding HBM lines. ASML is increasing EUV output. New power agreements are being signed with nuclear operators and utilities.

What we find interesting is the sequencing. The commitment came before the capacity. The denominator was the constraint when the numerator was announced. That is a structural feature of how this market is operating in 2025, and the filings describe it clearly for anyone who reads both sections of the same report.

We are watching this closely. The first indicator will be the Q1 and Q2 2025 earnings disclosures from each hyperscaler. Specifically: whether stated capex is tracking to guidance, and whether management language around supply chain availability has changed from the language in the annual filings.


primary sources

every figure cited

All data in this note comes from public annual filings, earnings call transcripts, or official company disclosures. No third-party financial data vendors were used. Where exact filing page numbers are provided, they refer to the PDF version of the filing as submitted to the SEC or relevant exchange regulator.

filing / source company period what it discloses
10-K (Form 10-K) Alphabet / Google FY2024 (filed Jan 2025) $52.5B capex; supply chain dependency risk factors; semiconductor procurement disclosure
10-K (Form 10-K) Microsoft FY2024 (filed Jul 2024) $55.7B capex; TSMC and NVIDIA dependency disclosures; AI chip supply risk
10-K (Form 10-K) Meta Platforms FY2024 (filed Jan 2025) $37.3B capex; $60–65B 2025 guidance; AI hardware supply chain risk factors
10-K (Form 10-K) Amazon FY2024 (filed Feb 2025) Capital expenditures; data center power and capacity constraints; supply chain risk
10-K (Form 10-K) NVIDIA FY2025 (filed Feb 2025) $130.5B revenue; data center $115.2B; TSMC dependency; CoWoS packaging dependency; customer concentration (top customers: 41% of revenue)
Annual Report ASML Holding FY2024 (filed Jan 2025) 44 EUV systems shipped in FY2024; High-NA EUV initial production; order backlog
Investor guidance TSMC Q4 2024 earnings (Jan 2025) $38–42B capex guidance for 2025; CoWoS capacity expansion timeline
Earnings call transcript Alphabet Q4 2024 (Jan 2025) $75B 2025 capex guidance; management language on AI infrastructure returns
Press release / blog post Microsoft January 2025 $80B AI infrastructure announcement for fiscal 2025; geographic breakdown
Earnings call transcript Meta Platforms Q4 2024 (Jan 2025) $60–65B 2025 capex guidance; Zuckerberg commentary on aggressive AI investment
Earnings call transcript Amazon Q4 2024 (Feb 2025) Jassy commentary on AWS demand exceeding capacity; data center and power bottleneck
PJM interconnection queue data PJM Interconnection 2024 queue report 280+ GW pending interconnection requests; average processing timelines